Nigeria caps electricity supply to Benin, others to meet domestic demand

The Nigerian Electricity Regulatory Commission (NERC) is set to boost electricity supply to domestic customers following its order mandating the System Operator (SO) to start capping power supply to international customers, which include neighbouring Benin Republic, Niger and Togo.

The SO, is a department in the Transmission Company of Nigeria (TCN).

In the NERC Order dated April 29, 2024, tagged: ‘Interim Order on Transmission System Dispatch Operations, Cross-border Supply and Related Matters’, the power sector regulator said the directive, which will last for six months in the first instance before review, takes effect from May 1, 2024.

Jointly signed by the commission’s chairman, Sanusi Garba, and vice chairman, Musiliu Oseni, the NERC’s interim cap order on international customer capacities for six months aimed to minimise impacts on domestic Gencos’ supply obligations.

NERC said the system operator’s sole reliance on limiting Discos’ load off-take/allocation in managing recurring grid imbalances while prioritising international off-takers and Eligible Customers (ECs) was neither efficient nor equitable.

The practice so far adopted by the operator in managing generation availability, it said, has caused significant hardship to DisCos’ customers, comprising industrial, commercial, and residential, especially during peak demands while prioritising delivery to other bilateral contracts, including export to international customers.

The commission noted that the current international and bilateral contracts with Generation Companies (Gencos) were based on best-endeavour and with loose terms that are often below the minimum contract standards currently operated in the industry.

It said many of the off-takers contracted bilaterally by Gencos often abuse this prioritisation and raise their off-takers during peak operations beyond their contracted levels at the expense of other grid users without attendant penalties for violation of grid instructions.

According to NERC, the order serves as an interim measure to guide the operations of the system operator and the TCN to implement Standard Operating Procedures (SOPs) to improve transparency and fairness of grid operations in delivering better services to all customers.

It urged the system operator to place interim caps on capacities supplied to international customers for six months from the effective date of the order, thus minimising the displacement and impact on domestic supply obligations by Gencos.

“The commission hereby orders as follows: The system operator shall develop and present to the commission for approval within seven days from the issuance of this order a pro-rata load-shedding scheme that ensures equitable adjustment to load allocation to all off-takers — Discos, international customers, and eligible customers — in the event of a drop in generation and other under-frequency related grid imbalances necessitating critical grid management.

“The system operator shall implement a framework to log and publish hourly readings and enforce necessary sanctions for violation of grid instructions and contracted nominations by off-takers in line with the grid code and market,” it stated.

Among others, it further directed that the system operator shall publish and notify all market participants and the commission of the previous day’s hourly log readings of off-take by market participants and the market settlements report by 12:00 noon of the next day.

“The system operator shall ensure that the maximum load allocation to international off-takers in each trading hour shall not be more than six per cent of the total available grid generation.

“The aggregate capacity that can be nominated by a generating plant to service international off-takers shall not be more than 10 per cent of its available generation capacity unless in exceptional circumstances a derogation is granted by the commission.

“The system operator shall henceforth cease to recognise any capacity addition in bilateral transactions between a generator and an off-taker without the express approval of the commission,” it added.

It urged the system operator and TCN to immediately initiate and install integrated Internet of Things (IoT) meters at all off-take and delivery points of eligible customers, bilateral supplies, cross-border trades, and outgoing 33kV feeders of the Discos to provide real-time visibility of aggregate offtake by grid customers.

“The installation of and streaming of data from the IOT meters should be completed within three months from the date of this order,” it added.

It is now possible to live in Nigeria and earn salary in US Dollars with premium domains, you can earn as much as $17,000 (₦27Million) Click here to start.

Nigeria supplies a portion of the electricity it generates to some of its neighbours, including the Benin Republic, Niger Republic, and Togo.

In the order, the regulatory agency directed that power delivery to Nigeria’s neighbours must not exceed six per cent of total grid electricity at any point in time.

The electricity sector regulator stressed that following the implementation of the April 2024 supplementary order, the commission had observed sub-optimal grid dispatch operation practices.

It argued that this has compromised the Distribution Companies’ (DisCos) ability to deliver on its Service Based Tariff (SBT) committed service levels to end-use customers with a significant impact on market revenues.